Home MenuReed Market Bridge Project
Improvements to the Reed Market Road railroad overcrossing are coming, enhancing travel time reliability for pedestrians, bicycles, and vehicles traveling east-west through Bend. These upgrades aim to make travel more efficient and convenient for everyone.
UpdatesLocationScheduleFundingBackgroundDocumentsPublic MeetingS & FAQ'sRelated Projects
Reed Market Road is a vital east-west arterial in southeast Bend. It is the only road south of Greenwood Avenue that connects 27th Street to the west side of the river. However, every day 6-8 trains cross the road and can stop traffic in excess of 20 minutes.
Big changes are coming to eliminate the at-grade railroad crossing and replace it with a bridge that places Reed Market Road over the railroad.
The project has been selected to receive federal funding and is being delivered in several stages – see below for the estimated timeline. As part of the preliminary engineering and environmental review effort, the City will be undergoing an alternatives analysis process that will review:
- Cross-sectional elements
- Intersection connectivity – particularly Ninth Street and American Lane
- Potential for pedestrian and bicycle undercrossings of Reed Market Road
Project Updates
Location
SE Reed Market Road starting at SE American Lane, over the railroad, through SE 9th Street, continuing past SE Quill Place.
Schedule
- Summer 2024 – Winter 2025/26: Preliminary Engineering and Environmental Review
- Winter 2025/26 – Winter 2026/27: Final Design and Right-of-Way Acquisition
- Mid 2027 – 2029 Construction
Funding
This project is currently funded through the Preliminary Engineering and Environmental Review phase through a 60/40 split between a grant from the Federal Rail Administration (FRA) and the 2020 Transportation General Obligation (GO) Bond, respectively.
The remainder of the design and construction has been awarded grant funding through the FRA in the amount of approximately $32M. The City anticipates signing a grant agreement for these funds in 2026. The local match for construction is 30% of total funds received and will be funded by the 2020 Transportation General Obligation (GO) Bond.
Background
Improvements to the Reed Market Road railroad crossing were previously identified in the City’s community-driven Transportation System Plan update undertaken between 2018- 2020. The plan was adopted by Bend City Council and projects from the plan were included in the Transportation General Obligation (GO) bond passed by Bend voters in November 2020. In 2021, this project was ranked highly in the project prioritization effort completed by the Transportation Bond Oversight Committee.
Project Documents
Public Meetings
- November 3, 2025 Open House #2
This open house comment period is now closed. However, you can still view the open house information. - December 2024 Pre-Design Open House #1
This open house comment period is now closed. However, you can still view the open house information