Reed Market Road is a key east-west connector and the intersection at 15th Street is nearing capacity. Users have reported safety concerns and congestion at this roundabout due to an inconsistent layout.  

The Transportation System Plan calls for expanding the partial multi-lane roundabout to a full multi-lane roundabout to improve connectivity, capacity and safety of the intersection.  

The project team will look at traffic data and other concerns to develop a concept to improve the roundabout and ensure safe crossings for people walking or riding bikes. 

Project Updates

Subscribe for Project Updates

* indicates required

Location

Map showing the roundabout intersection and key bike routes in the surrounding area

The intersection of Reed Market Road and 15th Street is a critical connection from Century Drive in west Bend to SE 27th Street, and from Greenwood Avenue to Murphy Road. There are several other important transportation projects underway or soon to begin that tie into this work as well, marked in yellow on the map.

Project Benefits 

Improvements to the roundabout will aim to reduce congestion and make it easier to navigate for all users. These improvements will be especially important as traffic volume continues to grow with the population. 

  • The improvements will reduce congestion by providing two lanes to enter the roundabout and two lanes to exit, which will allow more vehicles to travel at the same time. The current roundabout has two lanes entering but just one lane to exit.
  • To simplify navigation, all approaches will be redesigned so they’re both intuitive and as similar as possible.   
  • Pedestrian crossing locations and design will be improved to prioritize safety for people riding a bike or walking.
  • Improvements will also bring the roundabout up to current ADA accessibility standards.

Estimated Schedule

  • August 2024: Request for Proposals for design services for the project
  • November 2024: Council approval of design services contract
  • Winter 2024/2025: Begin design process 
  • End of 2026: Design complete 
  • Spring 2027: Start Construction 
  • End of 2027: Complete Construction

estimated project timeline

Funding

The project budget is $1.5M funded by the Transportation General Obligation (GO) Bond approved by voters in 2020. 