Home MenuAwbrey Butte Waterline Improvement Project
This project provides water distribution system upgrades to the Awbrey Butte area with eight interrelated water improvement subprojects and a portion of the adjacent Portland Avenue Improvements.
UpdatesScheduleConstruction Information & ResourcesDocumentsRelated Projects
Project Status
Estimated Completion
Spring 2025
Project Updates
- 12/19/2024 4:00 PM
Awbrey Waterline Improvement Project Update - Dec. 19, 2024
- 11/08/2024 12:00 PM
REMINDER: Portland Avenue Closure Begins Nov. 12
- 09/13/2024 4:00 PM
AWBREY BUTTE WATERLINE IMPROVEMENT PROJECT - 9/13/2024
- 07/12/2024 10:00 AM
Awbrey Waterline Improvements Project Update – July 12, 2024
- 05/24/2024 2:00 PM
Awbrey Waterline Improvements Project Update – May 24, 2024
- 05/08/2024 4:15 PM
Awbrey Butte Waterline Improvement Project Update – May 8, 2024
- 04/19/2024 3:33 PM
Awbrey Butte Waterline Improvement Project Update – April 19, 2024
Project Schedule
The project design and construction was completed in phases. The schedule below will be updated as more information becomes available and is subject to change.
This project uses an alternative delivery method known as Progressive Design-Build, which means some of the design will overlap with portions of construction throughout the project.
Individual properties in the construction area may not be impacted for the entire duration of the construction schedules presented below.
Fall 2021 - May 2022: Contractor and Engineer Selection
June 2022 - Spring 2024: Design
Spring 2023 - Spring 2025: Construction
- June 2023 - Fall 2023: Subproject 1
- September - October 2023: Subproject 3
- October - November 2023: Subproject 6
- November - December 2023: Subproject 4
- November 2023 - Spring 2024: Subproject 5
- Early 2024 - Summer 2024: Subproject 2
- Early 2024 - Fall 2024: Subproject 7
- Early 2024 - Fall 2024: Subproject 9
- Early 2024 - Spring 2025: Subproject 8