Urban Rate
A 30% reduction in applicable transportation SDC for uses in areas identified on the Urban Rate Area map adopted by City Council in the Fee Resolution. To qualify, the development must be in one of these areas, at least three stories high, the first floor of developments with frontage on arterial, collector, or for developments in the Bend Central District, main streets as identified in BDC Chapter 2.7, must be “commercial ready” as defined in BDC Section 2.7.3245.A. 1., 2., and 3. Rate is not available for development that includes any auto-dependent or auto-oriented uses (as defined in the BDC) or for single-unit or middle housing residential uses. Multi-unit residential does qualify if the other criteria are met.
The map below is the City of Bend's GIS map of the Urban Rate Area. Click here to go to the City of Bend GIS map.
Medical Overlay
The Medical Overlay District as defined in BDC Chapter 2.7 Article IV. Transportation SDCs in this District are charged based on ITE 720 w/in or near the hospital campus rate.
Southeast Expansion Area Supplemental Sewer SDC
The Southeast Area Pump Station Project (SEAP) was included in the City’s Capital Improvement Plan. The main goals of the Project were to increase overall sanitary sewer system capacity, efficiency, and connectivity for properties within the Southeast Expansion Area (SEA) and adjacent developments. The Project consists of a sewer pump station, sewer force main and associated gravity conveyance mains to provide sewer capacity for future urban levels of development in the SEA. As identified in the SEAP, this extended serviceability, and additional capacity will help promote development within the SEA and adjacent areas.
The SEAP also identified funding strategies including “evaluate and implement areawide funding tools (e.g. supplemental system development charges) needed to catalyze infrastructure development.” A 50/50 public/private funding split was among the funding packages presented in the SEAP. On May 1, 2024, Council provided direction to pursue a modified 50/50 funding split, as described in this methodology.
This methodology sets out recovery of 50% of adjusted project costs through a supplemental sewer SDC reimbursement applied to the limited geographic area which is served by the Project.
Southeast Area Pump Station Project | City of Bend
The map below is the City of Bend's GIS map of the special assessment areas. Click here to go to the City of Bend GIS map.
Contact development@bendoregon.gov for more information.